Earlier this year, amendments were made to the Planning Act 2016 to allow the Minister to extend or suspend periods under the Act because of the impact of COVID-19. On 8 July, the Minister extended timeframes for approved development by SIX months.
We understand that the additional time provided through this extension notice applies to development approvals in effect on 8 July 2020 or which come into effect between 8 July 2020 and 31 October 2020.
For example, a development approval that would have ordinarily lapsed on 1 August, 2020 now won’t lapse until 1 February 2021.
The extension notice does not revive lapsed development approvals, and does not apply to building work approvals to which section 71 of the Building Act 1975 applies.